Environment Ministry to submit Lavasa housing project report

By ANI
Tuesday, January 18, 2011

MUMBAI - The Ministry of Environment is expected to file its reply on Lavasa housing project before the Bombay High Court today.

In the report finalised on Monday, the ministry has reportedly said that status quo must be maintained at the site till a final order is given by the Bombay High Court.

The Lavasa Corporation had moved the High Court, accusing Jairam Ramesh of turning the issue into a personal concern and victimizing the company without evidence.

The fate of Lavasa, planned across 25,000 acres in Baramati district near Pune, hangs in balance after objections were raised over the ecological impact of the project by MoEF and several non-government organizations.

Earlier, the eleven-EAC led by Naresh Dayal last week visited the Lavasa and submitted its report to the MoEF on January 10.

The construction of the project was held up for want of environmental clearance.

On November 25, the MoEF had issued a stop-work notice for the Lavasa project saying it violated some environmental rules.

The Ministry of Environment and Forests had stayed construction work at the site alleging that Lavasa Corporation had violated the ministry notifications issued in 2004.
The court had earlier directed Lavasa to approach the ministry by December 9 regarding the stay imposed on the work and directed the ministry to pass an order on it by December 16.
However, the Ministry refused to vacate the stay and reply to the show cause notice. (ANI)

Filed under: India

Tags:
YOUR VIEW POINT
NAME : (REQUIRED)
MAIL : (REQUIRED)
will not be displayed
WEBSITE : (OPTIONAL)
YOUR
COMMENT :